WIS 441 System Interchange Construction

Select a date range from the dropdown menu     or drag the blue dot      to move through the timeline to control map results. Check out the latest WIS 441 System Interchange construction project brief.
‍

Drag the blue dot      to move through the timeline to control the map results.

Schedule:

Select a year or stage.

Traffic Impacts:

Select a year or stage.

Detours:

Select a year or stage.

Schedule:

Now through November 2026

Traffic Impacts:

Inside lanes closed on eastbound and westbound County OO between the WIS 441 ramps
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.

Schedule:

March through June 2027

Traffic Impacts:

1
Ballard Road northbound on-ramp closed from spring to summer 2027
2
Northbound I-41 to southbound WIS 441 system ramp closed from spring to summer 2027
3
County OO southbound off-ramp from WIS 441 closed from spring to summer 2027
WIS 441 northbound and southbound: lane closures and reduced capacity from spring 2027 to fall 2028
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
1
2
3

Schedule:

July through October 2027

Traffic Impacts:

4
Northbound WIS 441 to southbound I-41 system ramp closed from summer 2027 to summer 2028
WIS 441 northbound: lane closures and reduced capacity from spring 2027 to fall 2028
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
4

Schedule:

April through May 2028

Traffic Impacts:

4
Northbound WIS 441 to southbound I-41 system ramp closed from summer 2027 to summer 2028
5
Southbound I-41 to southbound WIS 441 system ramp closed spring to summer 2028
WIS 441 northbound: lane closures and reduced capacity from spring 2027 to fall 2028
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
4
5

Schedule:

June 2028

Traffic Impacts:

5
Southbound I-41 to southbound WIS 441 system ramp closed spring to summer 2028
6
Ballard Road southbound on-ramp closed spring to summer 2028
7
County OO northbound on-ramp to WIS 441 closed spring to summer 2028
WIS 441 northbound: lane closures and reduced capacity from spring 2027 to fall 2028
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
5
6
7

Schedule:

July 2028

Traffic Impacts:

7
County OO northbound on-ramp to WIS 441 closed spring to summer 2028
WIS 441 northbound: lane closures and reduced capacity from spring 2027 to fall 2028
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
7

Schedule:

August through October 2028

Traffic Impacts:

Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.

Schedule:

April through May 2029

Traffic Impacts:

8
Ballard Road northbound off-ramp closed spring 2029
9
Northbound WIS 441 to northbound I-41 system ramp closed spring 2029
Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.
Click here to download a pdf file.
8
9

Schedule:

June through August 2029

Traffic Impacts:

Expect off peak lane and ramp closures throughout construction. Stay alert for active work zones in the project area. All schedules subject to change.

Let's stay in touch

Submit a comment about the project

We welcome your feedback! Click the link below to share your comment.
Share Comment

Sign up to receive email updates

We deliver updates to your inbox! Click the link below to sign up for our distribution list.
Get Emails